ENVIRONMENTAL PROGRESS SUMMARY TABLE for the NAVAL EDUCATION & TRAINING CENTER SUPERFUND SITE, NEWPORT, RI - MAY 17, 2007

 

 

SITE NAME

ESTIMATED EXPENDITURE TO DATE

ESTIMATED COST TO COMPLETE

AVG.  ANN. MONITORING COST

CURRENT PHASE  (DATE1)

 

NEXT STEP(S) & PROJECTED DATE

 

IS SITE DONE?

 

 

CLEANUP ACTION TAKEN?

PROJECTED DATE FOR COMPLETION

OUTSTANDING ISSUES (SEE KEY)

McAllister Point Landfill (OU1, Site 1)

$1,415,061

 

$160 K/year

O&M

12 Feb 1997

DF Addendum to LTMP (May 07) & ESD (Sep 07)

YES

11.5 acre RCRA C cap

N/A

E; F; J

McAllister Point Landfill – Marine Sediment (OU4, Site 1)

 

 

$250 K/year

O&M

13 Sep 2005

DF Addendum to LTMP (May 07)

YES

46,270 tons sediment dredged; 86 tons metal removed; 19 tons submarine netting removed

N/A

E; F

Derecktor Shipyard (OU5, Site 19)

$475,668

$8.7 M

 

FS

12 Feb 1996

Resolution of FS comments (Jun 07) & Removal completion (Dec 07)

NO

60 cy Sandblast grit removed; xx cy soil removed

 

Dec 2010

A; B; K; M; J

OFFTA & SWOS (OU3, Sites 9 & 20)

$3,080,824

$8.6 M

 

FS

23 Mar 1992

Resolution of FS comments (Sep 07)

NO

Xx tons Soil removed

Sep 2011

A; B; E; F; G; H; I; J; K; L; N;O

Gould Island, Former Bldg. 32 (OU6, Site 17)

$1,481,900

$4.5 M

 

RI

5 Aug 2004

Phase II RI Work Plan (Mar 08)

NO

Xx tons PCB contaminated soil removed

2014 +

J; M

NUSC Disposal Area (OU7, Site 8)

$660,375

$4.5 M

 

RI

28 Sep 2006

RI field work (May 07)

NO

Xx cy Paint cans & drums removed

2014 +

J; L; M

Tank Farm 1 (Site 7)

 

$1.1 M

 

SI

SI Work Plan

NO

DESC cleanup under RIDEM UST regs

2014 +

B; G; J; L; N; O

Tank Farm 2 (Site 10)

 

$1.1 M

 

SI

SI Work Plan

NO

DESC cleanup under RIDEM UST regs

2014 +

B; G; J; L; N; O

Tank Farm 3 (Site 11)

 

$1.1 M

 

SI

SI Work Plan

NO

DESC cleanup under RIDEM UST regs

2014 +

B; G; J; L; N; O

Tank Farm 4 (Site 12)

$1,054,434

$1.7 M

 

SI

Data gap report (Aug 07) & Removal completion (May 07)

NO

Xx tons Soil removed

Sep 2011

B; G; J; L; N; O

Tank Farm 5 (OU2, Site 13)

$1,498,375

$1.7 M

 

PP

23 Mar 1992

Data gap report (Aug 07), Removal completion (May 07), & PP

NO

Xx tons Soil removed; xx gallons Groundwater pumped & treated system at Tanks 53 & 56

Sep 2011

B; G; J; L; N; O

Coddington Cove Rubble Fill Area (Site 4)

$191,723

$2.3 M

 

SD

SI Work Plan (2010)

NO

None; Site access restricted via a fence

2014 +

J

Melville Water Tower (Site 21)

 

$750 K

 

SI

Action Memo (Jun 07) & Removal Completion (Dec 07)

NO

Tower removed; Soil to be excavated in summer 2007

2008

None

Carr Point (UXO Site  1)

 

$1.9 M

 

SI

RI Work Plan

NO

None

2014 +

None

1Date of Remedial action completion for O&M sites or date of investigation start
KEY TO OUTSTANDING ISSUES, IMPEDIMENTS TO PROGRESS, & AREAS OF DISAGREEMENT

 

A:        Clean Up goals

B:         Area or volume of excavation or remediation

C:            Number of samples

D:            Location of samples

E:            Frequency of monitoring

F:         Type of monitoring

G:            Interpretation of regulations regarding whether a sheen constitutes free product (i.e., DNAPL)

H:            Authority of regulatory agencies (e.g., field decisions; post-ROD authority)

I:            Appropriateness of future or existing land use

J:            Enforceability of institutional controls (e.g., fishing advisories; in-place instruction; site access)

K:            Remedy selection

L:            Background or naturally occurring concentrations

M:       Site boundaries

N:        Non-CERCLA regulated compounds (e.g., TPH)

O:            Removal of potential source areas (e.g., underground piping)

 

***************************************************************************************************************************

KEY TO PHASES OF CLEANUP

 

SD:      Site discovery

PA:              Preliminary Assessment

SI:        Site Inspection (sometimes referred to as a SASE – Site Assessment Screening Evaluation)

RI:              Remedial Investigation

FS:              Feasibility Study

PP:             Proposed Plan (sometimes referred to as a PRAP – Proposed Remedial Action Plan)

ROD:            Record of Decision

RD:              Remedial Design

RA:            Remedial Action

O&M:            Operation & Maintenance