ENVIRONMENTAL PROGRESS
SUMMARY TABLE for the NAVAL EDUCATION &
As of March 19, 2008
|
SITE NAME |
ESTIMATED EXPENDITURE TO DATE |
ESTIMATED
COST TO COMPLETE |
AVG. ANNUAL MONITORING COST |
CURRENT
PHASE (DATE1) |
NEXT STEP(S)
& PROJECTED DATE |
SITE REMEDY ACHIEVED? |
CLEANUP
ACTION TAKEN? |
PROJECTED
DATE FOR COMPLETION |
ISSUES (SEE KEY) |
|
McAllister Point Landfill (OU1, Site 1) |
$25.5 M |
$5.7 M |
$200K/year |
O&M 12 Feb 1997 |
- Continue annual
monitoring until 2034 - Final Addendum to LTMP |
YES |
11.5 acre RCRA C cap |
N/A |
E; F |
|
McAllister Point Landfill – Marine
Sediment (OU4, Site 1) |
Included in OU 1 Costs above |
Included in OU 1 Costs above |
$190K/year |
O&M 13 Sep 2005 |
- Continue annual
monitoring until 2034 - Final Addendum to LTMP |
YES |
46,270
tons sediment dredged; 86 tons metal removed; 19 tons submarine netting
removed;54.12
tons of metal debris was disposed of in April 2002 |
N/A |
E;
F |
|
Melville North Landfill |
???????? |
N/A |
N/A |
Site Closeout? |
Resolve Sheen issue with RIDEM |
YES |
10 acre Landfill removal |
N/A |
G |
|
Derecktor Shipyard
(OU5, Site 19) |
$9.1 M |
$9.3 M |
|
FS 12
Feb 1996 |
Final FS for Marine sediments (June 08) Risk assessment for on
shore areas (late 08) |
NO |
60
cy Sandblast grit removed; 15,868 tons of soil removed; 12,004 tons of
asphalt and 1016 tons of concrete removed;3,800 gallons of storm water disposed |
2021
(Offshore) & 2013 (Onshore) |
A; B; K; M |
|
OFFTA
& SWOS (OU3, Sites 9 & 20) |
$12 M 5.0 M (Norm) |
$7.0 M |
|
FS 23
Mar 1992 |
Draft Final FS revision (July 08); Revetment construction |
NO |
22,839 tons soil removed;2,523 tons of concrete debris; 24.4 tons
of scrap metal; 5 cy of asbestos; Additional excavation of 2500 tons of soil and concrete
2008. |
2021 |
A;
B; E; F; G; H; I; K; L; N;O |
|
|
$3.5 M+PCB RA |
$4.5
M |
|
RI 5
Aug 2004 |
Draft Final QAPP (July 08) and field invest (09)) |
NO |
4,501
tons PCB-contaminated soil and concrete removed |
2013 |
M |
|
Gould Island, Building 44 Demolition & UST Remediation |
NAVSTA
Funded[SSP1] |
N/A |
N/A |
N/A |
N/A |
YES |
366 tons of PCB-contaminated soil and concrete; [SSP2] 2,106 tons of scrap metal; 759 tons of asphalt roof material;
76 tons of wood and steel;4,841 tons of concrete roadway debris; and assorted
measures of asbestos removed; 8840 tons of TPH-contaminated soil and 326,416
gallons of water were removed at Bldg. 44 UST |
N/A |
|
|
NUSC Disposal Area-OU7, Site
8 |
$6.7 M ??? |
$3.6 M |
|
RI 28 Sep 06 |
RI fieldwork (Through Aug 08) & |
NO |
36 drums and 349 tons of soil were removed |
2021 |
L; M |
|
Tank
Farm 1 (Site 7) |
$2 M - DESC |
$1.1
M - Navy |
|
SI |
RI
Work Plan (Jun 09) |
NO |
DESC
cleanup under RIDEM UST regs |
2014 |
B;
G; L; N; O |
|
Tank
Farm 2 (Site 10) |
$2 M - DESC |
$1.1
M - Navy |
|
SI |
RI
Work Plan (Jun 09) |
NO |
DESC
cleanup under RIDEM UST regs |
2014 |
B;
G; L; N; O |
|
Tank
Farm 3 (Site 11) |
$2 M - DESC |
$1.1
M - Navy |
|
SI |
RI
Work Plan (Jun 09) |
NO |
DESC
cleanup under RIDEM UST regs |
2014 |
B;
G; L; N; O |
|
Tank
Farm 4 (Site 12) |
$6.3
M |
$1.7
M |
|
SI |
Data Gap Work Plan (June 08) & Risk assessment (2009) |
NO |
2,968
tons soil removed;19.9 tons of sediment and 3,930 gallons of water
removed from Ruin 2 oil/water separator |
2013 |
B;
G; L; N; O |
|
Tank
Farm 5 (OU2, Site 13) |
$7.5
M |
$1.7
M |
|
PP 23
Mar 1992 |
Data Gap Work Plan (June 08) & Risk assessment (2009); Treat
plant demolition 2009 |
NO |
33,313 tons soil removed; 11,366,200 gallons Groundwater
pumped & treated in system at Tanks 53
& 56; 20,503,388 gallons of tank ballast
water treated and discharged to POTW |
2013 |
B;
G; L; N; O |
|
Coddington Cove
Rubble Fill Area (Site 4) |
$125K |
$2.5 M |
|
SI |
SASE
Work Plan (Jun 10) |
NO |
None;
Site access restricted via a fence |
2014 |
|
|
Melville
Water Tower (Site 21) |
$620 K |
$220 K |
|
SI |
Final Removal Completion (Apr 08); Risk assessment (June 08) |
NO |
Tower
removed; 929 tons of soil excavated in summer 2007 |
2014 |
None |
|
Carr
Point (UXO Site 1) |
$1.4 M |
$1.9
M |
|
SI |
DF SI Work Plan (July 08) |
NO |
None |
2015 |
None |
1Date of
Remedial action completion for O&M sites or date of investigation start
KEY
TO OUTSTANDING ISSUES, IMPEDIMENTS TO PROGRESS, & AREAS OF DISAGREEMENT
A: Clean Up goals
B: Area or volume of excavation or
remediation
C: Number of samples
D: Location of samples
E: Frequency of monitoring
F: Type of monitoring
G: Interpretation of regulations regarding
whether a sheen constitutes free product (i.e., DNAPL)
H: Authority of regulatory agencies (e.g., field decisions; post-ROD
authority)
I: Appropriateness of future or existing
land use
J: Enforceability of institutional
controls (e.g., fishing advisories;
in-place instruction; site access)
K: Remedy selection
L: Background or naturally occurring
concentrations
M: Site boundaries
N: Non-CERCLA regulated compounds (e.g., TPH)
O: Removal of potential source areas (e.g., underground piping)
***************************************************************************************************************************
KEY TO PHASES OF CLEANUP
SD: Site
discovery
PA: Preliminary
Assessment
SI: Site
Inspection (sometimes referred to as a SASE – Site Assessment Screening
Evaluation)
RI: Remedial
Investigation
FS: Feasibility
Study
PP:
Proposed Plan (sometimes referred to
as a PRAP – Proposed Remedial Action Plan)
ROD: Record of Decision
RD: Remedial
Design
RA: Remedial Action
O&M: Operation & Maintenance
[SSP1]I am pretty sure this was a UST program effort
[SSP2]This was the amount that we researched out of the closeout report. This was a separate effort from the main PCB removal work.